Rabu, 25 November 2009

INTERNAL MEMO

from : General Manager Date : August 3rd
To : Production manager Re : Jersey Contract
URGENT : ORDER NO 184/34
1. The above client is threatening legal action if this order does not reach him before 25th sept we would probably win his case. He already owes us 17.000 which may well become a bad debt.
2. Cloth from Bonardi has now arrived we must start production this week.
3. Completion date must be brought to mid-september. Which means working overtime. Please advice me of the effect of this on all other order.

JW

Could you please check stock lines which we could offer as replacement.

Tidak ada komentar:

Posting Komentar